Europe 1191 Gas engine plant 99

Wärtsilä has announced it has won an EPC contract to supply a new 43 MW gas engine power plant to Finnish energy company EPV Energy . The contract includes a six-year service agreement.

Gas Turbine Forum (GTF) 2027
More info

Gas Turbine Forum (GTF) 2027

The new power plant will be used as flexible electricity generation to balance power supply as variable renewable energy increases its share of the Finnish power system.

The new power plant will be built on the existing Mertaniemi power plant site in Lappeenranta, Finland. It will operate with four Wärtsilä 34SG engines. Wärtsilä will provide maintenance planning and coordination, operational support, and advanced predictive maintenance based on digital analytics.

Rami Vuola, CEO of EPV Energy, said: “Flexibility is a key requirement for future power systems. Weather dependency in electricity generation is increasing while electricity demand continues to grow, creating a greater need for flexible solutions and rapidly dispatchable power generation capacity.”