Vietnam breaks ground on Phase 2 of Bac Ai pumped storage hydropower plant

  • 11 months ago (2025-02-25)
  • David Flin
Asia 995 Hydropower 155

Vietnam Electricity (EVN) held a groundbreaking ceremony on 22 Feb for Phase 2 of the Bac Ai pumped storage hydropower plant in Ninh Thuan province.

13th Gas Turbine Focus Conference and Exhibition 2026 (GTF 2026)
More info

13th Gas Turbine Focus Conference and Exhibition 2026 (GTF 2026)

The Bac Ai project, the country’s first pumped storage hydropower facility, will have a total installed capacity of 1200 MW, consisting of four 300 MW units. The project has a total investment of $830 million, financed through loans and EVN’s capital allocation. Unit 1 is scheduled to start operation in December 2029, and full project completion is expected in May 2031.