Simon Jewell , head of sales, data centre lead at Leep Utilities
Ask most people what's holding up data centre power connections, and they'll point to the grid: not enough capacity and too many projects competing for the same headroom. And while they’re not wrong, it’s not the whole picture.
In fact, the biggest constraint for developers today is decision-making – and more specifically, how early and well-informed they need to be.
The recent reforms from the National Energy System Operator (NESO) and Ofgem have moved the connections process from first-come, first-served to something closer to first-ready, first-connected. Queue position matters less than it used to. Readiness, credibility and evidence of genuine progress matter more.
Under the old connections process, many essential design and commercial questions could actually be decided or agreed once a connection date was secured. Developers prioritised getting the connection over finalising plans.
But this is no longer a safe approach. Today, at Gate 1, developers need preliminary evidence that a project is viable. To reach Gate 2, which is where they secure a firm connection offer, they need detailed designs and a high level of consent and readiness. And in addition, Ofgem is discussing the possible introduction of more milestones and evidence requirements specifically for data centre developers.
If you fall short at either gate, the project doesn’t progress to timeslot allocation. As a result of this shift, decisions that used to sit much later in a programme now have to be managed much earlier.
Metering strategy is one example. Where and how a site is metered not only affects the build phase of a project, it also has ongoing effects on distribution use of system (DUoS) and transmission use of system (TUoS) charges. It shapes a client's ongoing bill and the long-term value of the network asset.
It's a specialist, technical decision with real commercial consequences, and getting it right increasingly depends on modelling options early rather than defaulting to the simplest configuration once construction is under way.
Phasing is another example. Full power requirements are rarely delivered in one go, and regulators increasingly favour phased or ramped connections over single, one-off allocations. This structuring and phasing, and negotiating the ongoing release of additional capacity as a client's needs grow, is work that has to start at the outset rather than being bolted on once building begins.
The only real solution to the challenges posed by today’s operating environment is to start making those key decisions much earlier in the process.
None of this can be solved by infrastructure alone, and it can't be solved by a partner who only shows up once the physical build begins. It calls for a connections partner capable of sitting inside the project team from day one, across several disciplines at once.
That means genuine build and technical expertise, so metering, phasing and other core planning decisions are grounded in real network experience rather than a standard template. It means legal expertise, so the commercial and consent complexity of a large-scale connection is understood from the outset, not discovered as a delay further down the line. And it means a particular kind of flexibility: the ability to adapt a plan quickly when a client's requirements shift, without defaulting to "no" or starting again from scratch.
That flexibility is harder to build than it sounds. The harsh reality is that it only comes from teams that have delivered enough large, complex, multi-party projects (whether data centres or other extra-high voltage and major infrastructure schemes) to recognise where problems are likely to emerge and to have a credible answer ready when they do.
There's a commercial dimension too. Data centre connections often involve significant upfront and asset value payments, and a partner needs the balance sheet strength, and direct access to senior decision-makers, to stand behind commitments of that size reliably.
Processes and procedures are useful, but they only work if the organisation behind them has the financial and cultural fit to back its own flexibility with real commercial follow-through.
Grid capacity pressure isn't going away, and it is a genuinely difficult problem to manage. But data centre developers and consultants retain control over one important variable: who they choose to manage that complexity on their behalf.
On paper, independent distribution network operators (IDNOs) can look broadly similar. In practice, the experience of working with one can differ substantially from another, particularly once a project moves beyond the straightforward parts of a build and into more complex areas of power and connection.
So firstly, make sure you start with the most important early decision: the right choice of partner to support you on your journey to power and connection.