Nepal has received approval to import up to 350 MW from India this winter to meet domestic power demand following the damage caused to several hydropower projects caused by recent floods.
India’s Central Electricity Authority (CEA) has authorised the Nepal Electricity Authority (NEA) to procure electricity at competitive rates from the Indian Energy Exchange (IEX) for up to 17 hours a day. The approval is valid to the end of July 2027. Dirghayu Kumar Shrestha, Managing Director of NEA, said it will help Nepal manage the seasonal gap between domestic supply and demand.
Nepal will be able to import 300 MW through the Kataiya-Kushaha, Ramnagar-Surajpura, and Raxaul-Parwanipur transmission lines. The remaining 50 MW will be available through the New Nautanwa-Mainahiya transmission line.
Nepal’s power supply was affected by the damage caused to several hydropower projects in the central regions of the country by the severe floods in August. Projects with a combined capacity of 431 MW have remained disconnected from the national grid following the disaster.