Post - Articles

Mitsubishi Power wins CCGT order for 2.8 GW Taiwan power plant

  • 2 months ago (2025-09-08)
  • David Flin
Asia 977 Gas 444

Mitsubishi Power has won a full turnkey contract to provide a 2.8 GW CCGT power plant for the Tung Hsaio Power Plant owned by Taiwan Power Company in Tung Hsaio, Miaoli County, Taiwan, 130 m southwest of Taipei. The project will be conducted jointly with CTCI Corporation .

WFES 2026 (World Future Energy Summit)
More info

WFES 2026 (World Future Energy Summit)

The plant will consist of five M501JAC gas turbines. The total contract value is approximately €4.44 billion. The five units are scheduled to start operation sequentially from 2030 to 2031. Mitsubishi Power will supply the gas turbines, steam turbines, and auxiliary equipment, while CTCI will be responsible for construction and Balance of Plant. The generators will be supplied by Mitsubishi Generators.