The first unit of the Rooppur nuclear power plant in Bangladesh has completed its second connection trial to the national grid, supplying around 320 MW continuously for 30 hours.

All Energy 2027
More info

All Energy 2027

Although the initial plan was to conduct a trial supply for 10-24 hours, the operation continued for nearly 30 hours, exceeding the scheduled period. Following the successful supply, the unit was disconnected from the grid.

The Nuclear Power Company Bangladesh Ltd (NPCBL) said various operating parameters and performance of the turbine-generator system and related equipment are now being analysed to determine the next operational steps.

Zahedul Hasan, Managing Director of NPCBL said: “It is a matter of immense joy and pride for us to have successfully connected to the national grid for the second time and supplied 320 MW continuously for 30 hours, We are proceeding with the next steps by ensuring the highest standards of nuclear safety and following international standards and regulatory guidelines.”

When fully operational, the Rooppur plant will generate 2400 MW.