The surge in power demand from AI data centres has pushed global gas turbine supply far below demand. Lead times for new orders is currently up to six years.
Siemens Energy said that its order backlog and reservations were at 104 GW at the end of September, and the practice of paying non-refundable deposits to lock in production slots is widespread.
In the last 12 months, global new orders exceeded 100 GW, compared to a global annual production capacity of 60-70 GW. Sales of second-hand and jet-engine gas turbines have become alternative procurement channels, and HD Hyundai Heavy Industries has won 1684 MW of orders in the USA alone for land-based power generation built on its marine engine technology.
Siemens Energy announced that its gas turbine orders and reservations totalled 104 GW. Of that, confirmed order backlog was 65 GW, with 39 GW in reservations. GE Vernova said that the deposits for these slot reservations has been rising sharply, up 20 per cent on the cost a year ago.
The International Energy Agency (IEA) said that this explosion in growth of demand has been driven almost entirely by AI data centres. The IEA anticipates that global power consumption from AI data centres will double over the next 3-4 years. It said that the problem lies in the pace of procurement. Data centres typically take 1-2 years to construct, but building the required substations and transmission lines and gaining grid connection approval typically takes around 10 years. As a result, on-site power plants are growing in popularity, resulting in this flood of orders for gas turbines.