
Everllence has signed an agreement
with a US data centre to deliver 24 ×
18V51/60G gas engines. With a total
output of 480 MW, they will power a
hyperscale data centre operating com-
pletely off-grid.
The engines will run on natural gas
and meet required, strict emission
standards thanks to SCR and oxida-
tion catalysts. The modular setup
with 24 individual units will ensure
exibility and allow for rapid capaci-
ty expansion as the project’s energy
demand grows.
In the US, data centre operators
typically wait several years for a grid
connection. Everllence’s medium-
speed engines enable the customer to
immediately establish a power sys-
tem for the project site that is sepa-
rate from the grid.
Engine delivery is scheduled in
two phases, starting mid-2026 with
commissioning aligned to the data
centre’s expansion.
Ansaldo Energia has signed a contract
with Pacico Energy for the supply of
eight AE64.3A gas turbines, together
with the associated generators, for a
strategic power generation project
supporting a major data centre infra-
structure in Texas.
The agreement represents a signi-
cant milestone for Ansaldo Energia,
marking the company’s return to the
US new-build power generation
market after more than 30 years. The
rst deliveries are scheduled to begin
in 2027.
The Nordex Group has secured three
new orders in the US with a combined
capacity of more than 480 MW. The
contracts comprise the supply of 81
N163/5.X wind turbines. The names
of the customers and of the projects
were not disclosed.
US-based developer Pacico Energy
Korea has been selected as the sole
developer of the 2.13 GW Jindo Off-
shore Wind Integrated Cluster Phase
2 in South Korea. The cluster will
comprise Pacico’s Manho and Jindo
Baram offshore wind projects.
The two projects form the second
and third phases of Pacico Energy
Korea’s 3.2 GW Jindo Offshore
Wind Project Cluster.
The government-designated cluster
is located off the coast of Jindo
County in Jeonnam-Gwangju Spe-
cial Metropolitan City. The regional
government is the implementing in-
stitution for the development.
GE Vernova has been chosen by Quin-
brook for the third stage of the Super-
node Battery Energy Storage System
(BESS) project in Queensland.
Under the contract, GE Vernova
will provide power conversion, con-
trol and integration technologies
across all three stages of one of Aus-
tralia’s largest battery energy storage
developments.
Supernode is a large-scale battery
storage development located at a
key point in Queensland’s electricity
network. The batteries act as a buffer
for the power system, storing elec-
tricity when supply is high and re-
turning it to the grid when demand
increases or renewable generation
changes. This helps maintain a reli-
able electricity supply while en-
abling more renewable energy to be
integrated into the network.
Stages 1 and 2, which use GE Ver-
nova technology, are now in full op-
eration and are among the largest op-
erational battery energy storage
facilities in Australia’s National
Electricity Market. Stage 3 will add
a further 260 MW and 1216 MWh of
four-hour storage, bringing the full
Supernode development to 780 MW
and 3075 MWh at a single site.
ABB has been selected by ENGIE
Australia to modernise the Pelican
Point power station distributed control
system infrastructure.
Pelican Point is a combined cycle
gas turbine (CCGT) plant featuring
two gas turbines and one steam tur-
bine, generating a maximum capaci-
ty of 532 MW of electricity. Located
on the Lefere Peninsula it is a critical
infrastructure asset supplying elec-
tricity to South Australia, including
the city of Adelaide.
ABB will modernise the facility’s
Advant controllers to the latest AC
800M controller for one of the gas
turbines and the steam turbine to en-
hance the automation technology,
strengthen cyber security and im-
prove real-time monitoring.
Arenko has been selected to deploy
its Nimbus optimisation, asset man-
agement and trading platform at Ørst-
ed’s 300 MW/600 MWh Iceni battery
energy storage project, co-located
with the 2.9 GW Hornsea 3 offshore
wind farm in the UK. Iceni is the
world’s rst utility-scale battery di-
rectly integrated into offshore trans-
mission infrastructure.
Rather than securing a standalone
grid connection, the project will
share transmission assets and an on-
shore grid connection with Hornsea
3 and is scheduled to become opera-
tional in Q1 2027.
As one of the UK’s rst large-scale
‘pathnder’ co-location projects un-
der the Offshore Transmission Net-
work Review (OTNR), Iceni is de-
signed to improve coordination
between generation and storage as-
sets and maximise the efcient use
of existing grid infrastructure.
Iceni has been described by Ørsted
and the market as a ‘blueprint for the
future’ of co-located energy infra-
structure. As a Path Finder project it
is demonstrating how shared grid
connections between offshore wind
and battery storage can increase out-
put, improve system efciency and
reduce the need for additional net-
work build-out.
ABB has been selected by Statkraft
AS to upgrade the Vikfalli hydropow-
er complex in Vik municipality, 170
km northeast of Bergen on Norway’s
west coast. The order was booked in
the second quarter of 2026. Financial
details were not disclosed.
The contract covers the complete
modernisation of the control, protec-
tion, excitation and electrical infra-
structure, extending the life of assets.
The Vikfalli project comprises
three power stations – Målset (24
MW), Refsdal (92 MW) and Hove
(68 MW) – with a total of ve gener-
ating units. ABB’s project scope in-
cludes installation of the ABB Ability
System 800xA distributed control
system and monitoring platform,
which will be integrated with exist-
ing third-party turbine systems to
provide a unied operational envi-
ronment across the complex.
The contract covers complete mod-
ernisation and will deploy UNITROL
8000 excitation systems for all ve
generating units, advanced cyber se-
curity, low and medium voltage elec-
trical systems, vibration monitoring
and protection, digital solutions, ca-
ble supply and installation.
Hitachi Energy and Larsen & Toubro
(L&T) have received the award of Ned-
erwiek3 and LanWin5, the third and
fourth projects under their previously
announced multi-year Framework
Agreement with TenneT.
Nederwiek3 will connect to an on-
shore converter station in the munici-
pality of Geertruidenberg in the
South of the Netherlands, while Lan-
Win5 will deliver clean power from
the North Sea to Lower Saxony in
Germany. Together, the two links
will bring 4 GW of clean electricity
to the grid. Hitachi Energy and L&T
are already collaborating to deliver
Nederwiek1 and IJmuiden Ver Alpha.
The projects are designed as part of
the broader evolution toward an in-
creasingly interconnected European
grid, with future interconnections al-
ready embedded in their design. A
key target is the integration of Neder-
wiek3 to the British grid through the
LionLink interconnector, currently
under development.
Worley has been selected as the pre-
ferred Engineering, Procurement, and
Construction (EPC) contractor for the
planned new Connah’s Quay Low Car-
bon Power (CQLCP) project in Dee-
side, UK.
This is the next step in the potential
development of CQLCP, which, if
consented and developed, would be
constructed on land next to Uniper’s
existing power station. A DCO con-
sent application was submitted in Au-
gust 2025 with the decision expected
in the coming months.
The proposed new gas red power
station would connect into nearby
CO
2
transport and storage infrastruc-
ture as part of the HyNet industrial
cluster, enabling the captured CO
2
to
be transported to permanent offshore
storage facilities in repurposed de-
pleted offshore gas elds. The rst
phase of the project could be opera-
tional from 2030.
Danish construction company Per
Aarsleff A/S has secured a design-and-
build contract by Energinet for the
onshore infrastructure of Denmark’s
Bornholm Energy Island project. The
Island will connect future offshore
wind farms in the Baltic Sea to the
Danish and German electricity grids.
The contract, valued at DKK3.7
billion (€495 million), covers the
construction of facilities at two sites.
The largest facility will be built in
southern Bornholm, where electricity
from offshore wind farms will be col-
lected before being transmitted to
Germany and to Høje Taastrup on
Zealand, where the second facility
will be located to support the connec-
tion of the energy island infrastruc-
ture to the Danish grid.
The design phase is scheduled to
begin on August 1, 2026, with earth-
works and concrete works expected
to start at the end of 2027/beginning
of 2028. The land facilities are
planned for handover in 2030 and
2031, respectively.
Va tt enf al l h a s b ee n s el ec te d a s t h e w i n-
ning bidder to develop the Nordsøen
Midt (North Sea I Mid) and Hesselø
offshore wind farms in Denmark’s lat-
est tender.
The two projects are scheduled to
be fully operational by 2032 and will
have a combined capacity of at least
1.8 GW.
Va tt enf al l su bm it t ed t he lo we st b i ds
in both tenders, offering a Contract
for Difference (CfD) strike price of
DKK504 (€67.60) per MWh for
North Sea I Mid and DKK542
(€72.70) per MWh for Hesselø. The
awarded price will be guaranteed for
20 years from the commissioning of
each offshore wind farm.
Intelligent Globe Construction (IGC),
the engineering and construction arm
of Intelligent Group, has signed a part-
nership agreement with the Ministry of
Electricity and Renewable Energy,
represented by the Egyptian Electrici-
ty Transmission Company (EETC), to
implement a new 500 kV overhead
power transmission line.
The project covers the engineering,
procurement, installation, testing and
commissioning of Lot 2 of the 500
kV transmission line extending from
the Orascom Substation to El Ha-
wamdeya Substation.
The turnkey project is designed to
transmit electricity generated by
wind energy projects in the Gulf of
Suez to Egypt’s national electricity
grid.
The Nordex Group has received a new
order in Türkiye from Türkerler Hold-
ing for a total capacity of around 525
MW. The contract covers the supply
and installation of 72 N175/6.X tur-
bines and also includes a 10-year Pre-
mium Service agreement with an ex-
tension possibility up to 25 years.
The order is for the YEKA-5 R25
Sivas wind project in Sivas, where 72
units from the Delta4000 series will
be installed with 108 m hub height.
Installation of the rst turbine is
scheduled to start in the third quarter
of 2027. Thanks to good and consis-
tent wind conditions, the site offers
ideal conditions for the N175/6.X.
Doosan Enerbility has signed a con-
tract to build a combined cycle gas
turbine (CCGT) power plant in Mis-
fah, Oman, with a consortium led by
Qatar’s Nebras Power. The deal is
worth approximately Won930 billion
($670 million).
Doosan Enerbility will also directly
manufacture and supply the plant’s
core equipment, including the steam
turbine and generator. For the proj-
ect, Doosan Enerbility formed a con-
sortium with SEPCO-3, a power
plant construction specialist, to carry
out engineering, procurement and
construction.
The 1700 MW plant is targeted for
completion in April 2029. Once built,
it is expected to help meet electricity
demand and strengthen power supply
stability in the region.
Americas
Asia-Pacic
Everllence to power US
off-grid data centre
Nordex Group secures
over 480 MW of US orders
Arenko software selected
for BESS-wind project
ABB to modernise
Norwegian hydro plants
Aarsleff to build Bornholm
onshore facilities
Preferred EPC contractor
named for Connah’s Quay
Hitachi Energy and L&T
accelerate grid expansion
Vattenfall wins tender for
Danish offshore wind sites
IGC to build 500 kV line
in Egypt
Nordex Group secures
major order in Türkiye
Doosan Enerbility to build
CCGT plant in Oman
Developer selected for
Jindo offshore wind cluster
GE Vernova chosen for
Queensland BESS
ABB to modernise Pelican
Point control system
Ansaldo GTs for Texas
data centre
International
Europe
10
THE ENERGY INDUSTRY TIMES - SEPTEMBER 2026
Tenders, Bids & Contracts