
D
emand for data centres is ex-
periencing exponential growth.
Even in the worst case sce-
nario, McKinsey & Company pre-
dicts a 20 per cent growth through
2030. In its report, ‘Beyond com-
pute: Infrastructure that powers and
cools AI data centers’, Global data
centre demand is expected to grow at
a CAGR of 22 per cent and reach
220 GW by 2030 – nearly six times
larger than demand in 2020.
One potential bottleneck to this
growth, however, is the power need-
ed to run them. According to the In-
ternational Energy Agency (IEA),
electricity consumption from data
centres is estimated to amount to
around 415 TWh, or about 1.5 per
cent of global electricity consump-
tion in 2024. It has grown at 12 per
cent per year over the last ve years,
and is predicted to double to reach
around 945 TWh by 2030 in the
IEA’s ‘Base Case’, representing just
under 3 per cent of total global elec-
tricity consumption in 2030.
In an effort to meet this power de-
mand, data centre developers and
operators have been scrambling to
nd ways of meeting the electricity
needs of their power-hungry installa-
tions. While some are eyeing future
technologies such as small modular
reactors, most are turning to renew-
ables, primarily, or building gas tur-
bine-based power plants to address
their immediate needs. Yet the main
constraint is grid connection – a
problem that is particularly acute in
Europe.
During a recent press visit to Coun-
ty Dublin, Ireland, journalists had the
opportunity to look at a project that
offers a solution to the challenge.
Last month Pure Data Centres
Group (Pure DC), the hyperscale
cloud and AI data centre developer
and operator, together with AVK, a
provider of prime, standby and dis-
patchable power solutions for data
centres and AI infrastructure, an-
nounced the launch of Europes rst,
large-scale, on-site microgrid for a
data centre.
Located at the new Pure DC cam-
pus in Fingal, near Dublin city, the
microgrid will operate in island
mode as a fully independent electric-
ity supply system, capable of gener-
ating, storing and managing its own
power.
Essentially, it provides the opportu-
nity for dispatchable capacity to sup-
port data centre operations during
initial development phases, prior to
full integration with the national
electricity system as grid connection
capacity becomes available. Over
time, the campus is intended to oper-
ate as part of a hybrid energy cong-
uration, combining grid-supplied
electricity with on-site infrastructure
designed to enhance exibility, resil-
ience and system stability.
Commenting on the installation,
Pure Data Centre’s newly appointed
CEO, Gary Wojtaszek, said: “What’s
unique about this facility is that it’s
self-powered… They had a chal-
lenge – they couldn’t get connected
to the grid, [so] they built up a
self-generation facility. We’ve
solved a challenge the company has
been suffering with for years...
we’ve also provided a solution that
doesn’t consume a lot of water like
the older data centres did. And there
are also environmental solutions that
help you get to zero carbon.”
The microgrid system, which will
represent about a $1.5 billion invest-
ment when complete, has a total ca-
pacity of 110 MW across three inter-
connected Energy Centres (EC1,
EC2, EC3 at 30 MW each) plus a 20
MW Battery Energy Storage (BESS)
system. It serves a campus with an
operational load that currently stands
at 54 MW but is designed to scale to
90 MW. This means it also has the
potential to help stabilise the grid
when excess power is available.
The idea for the project was rst
hatched about seven years ago –
even before grid constraints became
an issue.
Ben Pritchard, AVK, recalled: “In
2019 data centres were built using a
very well-trodden path… but differ-
ent thinking had to be applied when
Pure Data Centre came to us and
said, we have this site in Dublin that
may never get a grid connection.
nd it was the rst time we saw that
waiting wasn’t an option; so we had
to think outside the box.”
The need for 99.999 per cent, or
ve nines, availability called for
AV K t o a d d “ a n o t h e r l a y e r ” o f t e c h -
nology to conventional solutions.
Pritchard added: “You know you
need a system of, say, 100 MW but
the ramp rate for the load is also
completely undened. o, you have
to design the system with a exibili-
ty that allows for seeing maybe only
for the rst six months, which
is very different to having an engine
that needs to run at full capacity.”
Drawing on its own expertise in
powering data centres with Pure
Data Centres’ expertise of the pro-
cess, the companies came up with an
integrated architecture that uses a
“tapestry of technologies”. A pilot 10
MW (max. output capacity) microg-
rid system was subsequently de-
signed and installed, and has been
running since 2024.
Pritchard noted: “Some see micro-
grids as a bridging solution but it’s
so much more than that. When we
rst started the conversation with
Pure [Data Centres], we didn’t know
whether there would ever be a grid
connection. So, we went into this de-
signing a scheme that wasn’t there
just for ve years to bridge a gap be-
cause at the time there was no visi-
bility on when a grid would come…
so we went into designing a scheme
that would be able to run for the
foreseeable lifetime of the facility.
“What we are experiencing with
this system is that we’ve built some-
thing that removes demand from the
grid; but also, when that system gets
grid connected, it allows that infra-
structure to participate in grid activi-
ty its the rst time in Europe we
see data centres actually being a solu-
tion to the challenges of the energy
transition and mass grid demand.”
This “temporary” microgrid –
which is seen as the “blueprint” in
terms of performance parameters
and design considerations for how
microgrids will work in the future –
forms the basis for the new larger
installation. It uses a mix of several
2.5 MW MTU Rolls-Royce gas and
diesel engines, some of which can
run on hydrotreated vegetable oil
(HVO) when the gas engines or gas
network fail, and a 2 x 5 MW
BESS.
“This is ‘temporary’ in the fact that
it will one day be decommissioned,”
said Pritchard. “But everything that
we have designed into this scheme is
as complex as the larger scheme.”
Construction of the new scheme is
at an advanced stage. EC1 and EC2
are expected to be fully operational
around September 2026 and will be
followed by EC3 in 2027.
The larger installation is based on
9.8 MW Wärtsilä dual fuel engines –
six already installed (for EC1 and
EC2), with three more to come in the
future (for EC3). These medium
speed engines will run on natural gas
with 1 per cent HVO pilot fuel,
ready to switch to run 100 per cent
on the 72 hours’ worth of HVO bio-
fuel that is primarily kept for back-
up. The microgrid will also incorpo-
rate the existing pilot 10 MW BESS
alongside a new 10 MW BESS.
Apart from the need to reduce the
overall number of engines that
would be needed for the larger facili-
ty, and thereby the footprint, there
were other important drivers behind
the engine selection.
Bob Downing, VP Sales, Energy
Solutions at AVK, explained: “The
medium speed engines are bigger
power blocks, easier to control and
much more adaptable with load
changes. Also, the dual fuel capabili-
ty meets Ireland’s Secondary Fuel
Obligation for microgrids. So, you
have to be able to switch from natu-
ral gas to HVO.”
The obligation is specic to Ire-
land, and Downing points out that
technology choice depends on the
country. With the ability to provide
solutions based on fuel cells medium
speed and high speed engines, as
well as gas turbines, Downing says
the company is targeting microgrid
installations in a number of coun-
tries. With such systems already tak-
ing root in the US, this be-
hind-the-meter solution will no
doubt gain popularity elsewhere.
“We are talking to Germany, the
Netherlands, UK, more in Ireland,
and there’s also a lot of interest in
Spain and Portugal at the moment,”
said Downing.
And as the world continues to em-
brace renewables and the demand
for electricity continues to grow,
with data centres identied as a
strong driver, the developments at
Fingal look set to offer a blueprint
for data centre developers right
across Europe and beyond.
During a recent press visit to County Dublin, Ireland, journalists had the opportunity to look at a project that offers a
solution to the delays data centre developers are facing in bringing power to their facilities. Junior Isles
Powering data centres: a
blueprint for Europe
THE ENERGY INDUSTRY TIMES - APRIL 2026
15
Technology Focus
Artist impression of the data
centre near Dublin, where
construction is well underway